During the Dec. 19 administrative public hearing, the Board of County Commissioners approved a $1,268,560 agreement for the design completion of the Rosevale Road Drainage Improvement Project.
The project aims to complete a full drainage design for Rosevale Road to alleviate localized flooding.
The project will include:
- Geotechnical investigation
- Environmental, hydraulic, and hydrologic modeling
- Obtaining Right of Way (ROW) and permits
- Alternative analysis benefit-cost analysis
- Final design plans
The Federal Emergency Management Agency (FEMA) partially funds the design agreement through a grant award of federal funds.